Planned power work in Dupuis data centre 14 Feb Archived No-RSS

  • PPS will be installing new electrical service in the Dupuis data centre on Wednesday February 14 from 700 to 800 am.
    Part of the work will involve shutting down the load panel from the secondary UPS-B.
    ITS does not expect and interruption to data centre hosted services or equipment as a result of this work.

    This notification will be updated when the work is completed.
  • Publish Date: February 9, 2018 15:04
  • Channels: None
  • Lists/Email Addresses:
  • IT Support Centre